Home / Insights / Owner's Representation

Guide · Owner's Representation

What does an owner's representative cost in the UAE — and what should the scope include?

What owner's representation costs in the UAE, on a construction-cost basis — and the scope items most appointments quietly leave out.

Ask what owner's representation costs in this market and you will be given a percentage. You will rarely be told a percentage of what. That omission is not a detail — it is the reason two proposals that look comparable often are not.

What does an owner's representative cost in the UAE?

Across PRASOON's UAE engagements, owner's representation runs between two and eight per cent of construction cost. Construction cost means the contract value of the works — not total development cost, not total installed cost. The range is wide because the work is not proportional to the value of the building.

What moves a project through it is judgement, duration and headcount. A large single-asset build procured under a FIDIC contract sits at the lower end: the contract supplies most of the machinery and the representative is governing an established structure. A brand-flag hotel or branded residence sits higher, because operator approval rights add a second approval chain running alongside the authority chain. Multi-package developments sit higher than single-asset ones — the cost is in the interfaces, not the square metres. And two factors move it more than owners expect: an appointment beginning at strategic definition covers more stages and a longer duration than one beginning at construction, and an overseas owner who cannot attend monthly needs a reporting burden a Dubai-based owner does not.

A percentage is a reasonable way to check whether a proposal is in the right territory. It is a poor way to decide which proposal to accept.

Why does every other figure you find say something different?

Because almost none of them state what the percentage applies to. Published figures for this role range from one to seventeen per cent, calculated variously on construction cost, total project cost, total installed cost and development cost — used interchangeably across sources, without disclosure.

Work it through. A fee of AED 12 million on a project with AED 300 million of construction cost and AED 400 million of total development cost is four per cent on one basis and three on the other. Same fee, same scope, a full percentage point of apparent difference created entirely by the denominator. Compare two proposals that have each quietly chosen their own basis and the cheaper-looking one may be the more expensive.

The provenance is no better than the arithmetic. Trace the figures that circulate and they loop: a recruitment firm citing an owner's representation firm, citing market clusters it says it has observed, citing nothing. The only figures with named sources behind them trace to an analysis from 1999 and an undated dataset, surfaced by a practitioner who flags them as stale and asks publicly whether anyone has anything better. Nobody answers. There is a structural reason for that: professional bodies in the United States stopped publishing fee schedules on antitrust grounds and their British counterparts withdrew theirs under competition law. No institution is left whose job it is to publish this.

The UAE position is more specific. Dubai's 1998 executive regulation on engineering consultancy requires the consulting engineer to conclude a written contract specifying the agreed fees and the manner of payment. It prescribes no scale. Dubai Law No. 14 of 2025 then rebuilt the sector's regulation comprehensively — six categories of engineering office, Municipality classification, competency certificates, limits on outsourcing, ten-year record retention, penalties reaching AED 200,000 — and says nothing about fees at all.

Dubai regulates who may give engineering advice. It does not regulate what that advice should cost.

Why don't the standard forms price this as a percentage?

Because the drafters concluded a percentage prices the wrong thing. The only standard form in the world that defines the owner's representative role offers six ways to pay for it, and percentage of construction cost is not among them. Five of the six derive from people and time.

The form is C104-2024, published by the American Institute of Architects in June 2024. What makes its omission evidence rather than trivia is the comparison: the same institute's owner–architect agreement does permit a percentage of the owner's budget for the cost of the work. Percentage pricing was available to the drafters. They allowed it for the architect and withheld it for the representative.

How the standard forms price an owner's representative
BasisWhat it rewardsWhat it risks for the ownerWhen it suits
Stipulated sumDelivery within a fixed priceUnder-resourcing if scope moves and the sum does notWell-defined scope, fixed duration
Multiple of direct salary expenseTransparency of the resourced teamRequires the owner to audit timeLong appointments where scope will evolve
Multiple of direct personnel expenseAs above, with overhead disclosedSameSame
Fee plus expensesA stable management fee, costs passed throughExpense creep without a capVariable travel or specialist input
Hourly billing ratesPrecise payment for effort expendedOpen-ended without an upset limitAdvisory or interim appointments
Multiple of consultants' and contractors' billingSimplicity of administrationTies the fee to third-party costRarely, for owner-side roles
Percentage of construction costFee rises as the project gets more expensiveNot offered in the standard form; a comparison device only
The first six are the compensation bases set out in the American Institute of Architects C104-2024, Standard Form of Agreement Between Owner and Owner's Representative, June 2024. The institute makes no recommendation between them. The seventh row is not in the form.

The pattern repeats. RICS guidance on appointing a project manager publishes no percentage ranges at all — it sets out four fee bases, recommends an upset limit where fees are time-based, and where a percentage is used insists the cost base be defined and agreed rather than assumed. It also requires the appointment to fix key personnel, their qualifications and their resource allocation percentages, and weights key personnel at thirty to forty per cent in best-value selection, the largest single quality criterion. In Germany, the one committee anywhere publishing a structured fee standard for owner-side project management has moved in recent editions towards personnel-capacity benchmarks by cost bracket, explicitly to support time-based calculation rather than percentage tables.

The reason is not mysterious. A fee calculated as a share of construction cost rises when construction cost rises. That is a structural feature of the basis rather than an allegation about anyone's conduct, but it means the mechanism rewards the outcome the owner is paying the adviser to prevent. Drafters whose job is to write terms that work when relationships fail have consistently declined to build that in.

None of which makes a percentage useless. It makes it a comparison device rather than a pricing mechanism.

What should the fee actually be built from?

People and months. An owner's representation fee is a resourced team costed over a duration, with overhead, professional indemnity cover and margin on top. A proposal that cannot be broken into named roles, seniority, committed time and duration is not a fee. It is a number.

The inputs are published. Cooper Fitch's UAE salary guide, issued December 2024 from a survey of leaders across more than a thousand Gulf organisations, puts a project director at AED 55,000 to 78,000 a month, a senior project manager at AED 39,000 to 55,000 and a commercial manager at AED 21,000 to 38,000. Hays published a GCC guide in January 2026 drawing on more than 1,600 employers and professionals. Between them an owner has a starting point no circulating fee percentage can match.

A salary is not a fee — overhead, insurance, non-chargeable time and margin sit on top, and a credible proposal states that multiplier rather than burying it. But the build is what makes a fee interrogable line by line, and interrogable is what comparable means.

The largest cost driver is also the most frequently fudged: full-time against visiting. A project director resident on site and a project director attending two days a month are different propositions at very different costs, and both appear in proposals as "project director." Ask for committed time allocation per person per month, in writing, with a contractual commitment to continuity of named personnel.

Then close the loop. Run the build, express it as a percentage of construction cost, and see where it falls against two to eight. If a proposal sits at three per cent but its own resourcing schedule implies six, one of those numbers is wrong — better to know which before appointment than after.

What should the scope include as standard?

More than most appointments say. On a large UAE project the FIDIC contract supplies an architecture the scope can lean on: defined roles, notice regimes, determination machinery. Below that size there is frequently no standard form at all, and where there is no contract architecture the appointment document is the only governance the owner has.

That asymmetry is under-appreciated here. Large projects run predominantly on FIDIC forms, and owners on them inherit structure whether or not their scope of services is well drafted. Mid-size and smaller developments often run on bespoke or minimal contracts with none of it — and on those projects the scope of services is doing all the work, while usually being the thinnest document in the file. There is no UAE or Gulf equivalent of a professional work-stage framework to fall back on either. Stage gates here are regulatory permit gates, not a plan of work, so the mapping of scope to stages happens deliberately or not at all.

The owner's representative scope and authority matrix
What should be in scope as standard, and what is commonly left out
StageScope itemStandard or commonly excludedWhat evidences delivery
Strategic definitionBusiness case tested against optionsExcluded when appointed lateOption appraisal signed off by the owner
Strategic definitionBudget established with risk allowances identifiedStandardBudget with stated allowances, not a single figure
BriefProject brief approved and derogations recordedStandardApproved brief; derogations register
BriefProcurement strategy and contract form recommendedCommonly excludedStrategy paper comparing routes
BriefLimits of authority and reserved owner approvals definedCommonly excludedAuthority schedule in the appointment
DesignDesign reviewed against brief, budget and authority requirementsStandard as review, excluded as approvalComments register with responses closed out
DesignReview responsibility separated from design liabilityCommonly excludedExpress wording; PI position confirmed
DesignChange control established before design freezesCommonly excludedProcedure issued and adopted
TenderTender evaluation and award recommendationStandardEvaluation report, technical and commercial split
TenderProcurement of the executed contract, not merely awardCommonly excludedExecuted contract, not a letter of intent
ConstructionMonthly cost report: incurred and valued, incurred and estimated, forecast, risk allowancesStandard, rarely specified to this levelReport in the format agreed at the outset
ConstructionContractual notice machinery operated to timeCommonly excludedNotice register against contractual deadlines
ConstructionClaims and variation managementCommonly excludedVariation register with early-warning flags
ConstructionNamed personnel with committed monthly time allocationCommonly excludedResourcing schedule and attendance against it
HandoverSnagging, close-out and defects liability administrationStandard to practical completion, excluded thereafterDefects list closed out and signed off
Sources: RICS, Appointing a Project Manager (GN 107/2013) and Cost Reporting (2015); FIDIC Client/Consultant Model Services Agreement, 5th edition (2017), which requires the scope to state exclusions expressly; RIBA Plan of Work 2020 for the stage structure.

Two categories are consistently under-specified. The first is cost reporting. Published guidance is precise about what a cost report must contain — costs incurred and valued, costs incurred and estimated, forecast costs and risk allowances, updated monthly, with anticipated instructions carrying a cost allowance and unagreed valuations shown separately rather than absorbed. It advises against a general contingency in favour of identified risk allowances, and says the format should be agreed at the outset. Most appointments say "monthly cost report" and leave the rest to be discovered in month three.

The second is authority. Limits of authority are a fill-in field in the standard forms, not a default. The owner's representative agreement carries an explicit warning that the form limits the representative's authority. If your appointment does not state those limits, they are being set by conduct — and conduct creates apparent authority whether or not you intended it.

What is commonly excluded, and what does that cost you later?

Claims and variation management, design review liability, authority approvals coordination, and the operation of contractual notice machinery. Each is routinely absent from the scope, and each surfaces at the worst possible moment — when the owner discovers nobody was contractually responsible for it.

Notices are the sharpest of these in the UAE. Courts here and in the DIFC enforce contractual notice requirements strictly, and procedural failure can defeat a substantive entitlement regardless of merit. The question is not whether somebody reports on notices in the monthly. It is who is obliged to operate them, to time.

Design review and design liability must stay distinct. Guidance is explicit that project management and designer roles should be separate, and that if the project manager takes design responsibility the professional indemnity position needs checking with insurers. Appointments here routinely blur it: a scope saying the representative will "review and approve" design is doing something quite different from one saying "review and comment."

Scope headings are also read expansively against the consultant when tested. In a 2012 English Technology and Construction Court decision on a project manager's appointment, a scope covering contractor selection and appointment was held to extend to procuring the executed building contract itself, the court treating execution as fundamental rather than aspirational. The same decision found a positive duty to escalate rather than merely report. It is worth knowing on liability caps too: the cap was struck down as unreasonable because it sat far below the professional indemnity cover the appointment required the consultant to carry. In the standard forms that cap is a blank the owner fills, not a default, and one set well below the insurance the owner is effectively paying for may not survive challenge.

One local check to add to any appointment process: Dubai's 2025 consultancy law created licensed categories for engineering advisory and engineering audit offices. An adviser performing technical review or supervision in Dubai may be conducting a regulated activity requiring classification. Ask for it.

What happens to the fee if the programme extends?

On most appointments in this market, nobody has decided. The standard forms have: the owner's representative agreement contains a fill-in for the number of months beyond which the representative is compensated as additional services. Duration is priced by default. In bespoke UAE appointments it usually is not priced at all.

This is the most predictable cost event on a multi-year build and the one most likely to go unaddressed. When it arrives it resolves in one of three ways, none good. The adviser absorbs it and quietly reduces resourcing. The adviser claims it and the owner disputes it. Or the adviser demobilises the senior people, leaves juniors in place, and charges the same fee for a materially different service.

Specify four things instead: the assumed programme duration the fee is based on, the trigger at which extension compensation begins, the rate, and whether named-personnel commitments survive into the extension. The last matters most and is almost never written down.

How do you tell if a fee proposal is too low?

Compare it to the resourcing it implies, not to the other bids. FIDIC's guidance on selecting consultants states that cost-based selection should never be used, that technical weighting should never fall below eighty per cent, and that a proposal abnormally low against the client's own confidential pre-estimate should be treated as non-conforming rather than as a saving.

That threshold is not arbitrary. Below it, an evaluation becomes cost-based selection in substance whatever the scoring sheet says, because the price differential starts to outweigh any achievable quality differential. If your model weights fee at thirty per cent, you are running a price competition with a quality veneer.

The confidential pre-estimate is the part owners skip. Build your own resourced estimate before proposals arrive and treat a significant undershoot as a question rather than a discount. A fee below what the scope can be delivered for buys fewer people, more junior people, less of their time, and reporting that arrives too late to act on. The fee was never the exposure. The variation nobody caught is the exposure.

Three documents to request from every proposer, and to compare only against each other: named personnel with committed monthly time allocation, an explicit list of exclusions, and the assumed programme duration with its extension mechanism. A proposer who cannot produce all three has not given you something comparable to one who can.

Sources

  1. C104-2024, Standard Form of Agreement Between Owner and Owner's Representative — The American Institute of Architects, June 2024
  2. Appointing a Project Manager, guidance note GN 107/2013 — RICS, April 2013
  3. Cost Reporting, 1st edition — RICS, March 2015
  4. Client/Consultant Model Services Agreement (White Book), 5th edition — FIDIC, 2017
  5. Guidelines for the Selection of Consultants, 3rd edition — FIDIC, 2019
  6. Administrative Decision No. 51 of 1998 on the practice of engineering consultancy — Government of Dubai, 1998
  7. Law No. 14 of 2025 Regulating Engineering Consultancy Activities — Government of Dubai, 5 October 2025
  8. Salary Guide United Arab Emirates — Cooper Fitch, December 2024
  9. GCC Salary Guide 2026 — Hays, January 2026
  10. Heft Nr. 9, Projektmanagement in der Bau- und Immobilienwirtschaft, 6th edition — AHO, May 2025
  11. RIBA Plan of Work 2020 — Royal Institute of British Architects, 2020
  12. Ampleforth Abbey Trust v Turner & Townsend Project Management Ltd [2012] EWHC 2137 (TCC) — England and Wales High Court, Technology and Construction Court, 27 July 2012

Common questions

What percentage of construction cost should an owner's representative be?

Across our UAE engagements the range is two to eight per cent of construction cost, meaning the contract value of the works. Complexity, duration, interface count and whether the appointment starts pre-brief or at construction move a project through that range. Use the percentage to sanity-check a proposal, not to select between proposals.

What happens to the fee if the programme extends?

On most UAE appointments it is not addressed, which is why it becomes a dispute. Specify the assumed programme duration the fee is based on, the point at which extension compensation starts, the rate, and whether named-personnel commitments continue. The standard owner's representative agreement treats this as a fill-in field rather than an afterthought.

How do I tell if a fee proposal is too low?

Build your own resourced estimate before proposals arrive and compare against that, not against the other bids. FIDIC guidance treats a proposal abnormally low against the client's pre-estimate as non-conforming. A low fee buys fewer and more junior people, less of their time, and reporting that arrives too late to act on.

What is usually excluded from an owner's representative's scope?

Claims and variation management, design review liability, authority approvals coordination, and responsibility for operating contractual notice machinery. FIDIC's model services agreement requires exclusions to be stated expressly in the scope. Most appointments in this market do not do it, and the gaps surface only when something goes wrong.

How do I compare two proposals priced on different bases?

Convert both to the same denominator before comparing anything. Published figures for this role use construction cost, total project cost, total installed cost and development cost interchangeably, so a proposal quoting three per cent may be more expensive than one quoting four. Ask each proposer, in writing, what their percentage applies to.

When should the appointment start?

Before the brief is fixed, if the budget allows. The decisions that determine cost and programme outcomes — procurement route, contract form, project brief, budget, design-team selection — are made in the earliest stages. A representative appointed at construction stage inherits all of them and can only manage the consequences.

Keep reading

Talking through a live decision?

Bring the project. The first conversation is a working session, not a sales call.

Start a conversation